COMPLETED                                                           CITY OF BRUCE                                     

                               PROJECT NAME: LAGOON SOUTH PRIMARY POND

                          Proposed bids are due back by March 5,2021 Opened on March 9,2021 at 7:00 pm.

                            Start date April 15 ,2021 Completion date no later than May 30,2021

                          Any delays after May 30,2021 will be subject to a penalty of 250.00 per day.

                                       City of Bruce has the right to refuse any or all bids

  1. Job Consist of placing rock around 2 sides of sewer pond 3” to 6” oversize Natural Round Rock.

  2. Rock to be placed along the edge of Lagoon 1st side is 162’ second side 254’ in length Pond depth 4’ all work along the edge must be smooth finish for maintenance.

  3. Any unforeseen overages must be council approved.

       Any Questions Call City Maintenance at 651-3873 or City Office 627-5323                       

*********************************************************************************************************************************************************************************************************************

   COMPLETED                                                              CITY OF BRUCE

                                              PROJECT NAME: CAMP: SEWER REPAIR 2021-1               

                                                                        Sewer Line Repair

        Proposed bids are due back by March 5,2021 & Opened on March 9,2021 at 7:00 pm.

                     Start date April 15,2021 & Completed by May 30,2021

     Any delays after May 30,2021 will be subject to a penalty of 250.00 per day.

                             City of Bruce has Right to refuse any or all bids.

                                                Project consist of Repair SEWER LINE 8” Diameter 

  1. Excavate down to sewer line about 6’ down Cut out bad area about 20’ Length. Replace with sch 80 pipe. Finish to grade. Ready for grass seed done by the City of Bruce.
  2. Any unforeseen overages must be council approved.

 

   

       Any Questions Call City Maintenance at 651-3873 or City Office 627-5323

*********************************************************************************************************************************************************************************************************************

COMPLETED

                                                             CITY OF BRUCE                                   

                                        PROJECT NAME: DRAINAGE PROJECT 2021-1

                    Proposed bids are due back by March 5,2021       Bids are opened March 9,2021 at 7:00 pm.

                   This Project has a start date of April 15, 2021   A Completion date of May 30, 2021

                    Any delays after May 30,2021 will be subject to Penalty of 250.00 per day.

                                            City of Bruce has the Right to refuse any or all bids     

                                              All culverts are provided by the City of Bruce                                                                                                     

  1. Second Street from Madison to Jefferson Reset Culvert 5” to low (Cody’s driveway)       remove culvert reset old culvert to grade compact with crushed gravel.

        2. Second Street Julie’s driveway Replace with 18” culvert with aprons. (yellow house)

             Remove old culvert replace and set to grade with 18” galv. 20ft length culvert with aprons compact with crushed gravel.

        3. Ditch’s from Wagner to Madison both sides. Next area is on Madison between Frist to Second Street both side of Ditch. These Area’s need the ditches to blend in for safety                       and the ability for Maintenance.

        4. Ditch on the east side of (Ruden’s) Extend Sidewalk Culvert to north about 20’ cut & Blend Both sides of ditch for Maintenance.

        5. Second Street & Jefferson dig out old culvert Replace with 18” X 30’ length & aprons. Remove old culvert replace with 18” galv. 30’ length with aprons compact with crushed               gravel.

            Also haul some clay & black dirt in so it will drain to the east on south side of the culvert.

        6. Jensen’s Driveway needs aprons Also needs grading along both sides of ditch for Maintenance.

        7. Corner of Jay street & fourth street (truck Route) add to the west end (culvert we have). Add 20’ Culvert to east end with aprons. Cover 8ft. with crushed gravel to add to the                  radius compact the rest black dirt blend to match grade. (see Map)

        8. Culvert at Necia Benz needs to be reset deeper this was due to frost and pumping water all winter last year. Dig out existing culvert reset put to grade and Compact with                     crushed gravel.

        9. Any unforeseen overages must be council approved.

                                Any questions call City Maintenance at 651-3873 OR City Office 627-5323  


*******************************************************************************************************************************************************************************************************************

     COMPLETED      

                                                              CITY OF BRUCE                                     

                    PROJECT NAME: DRAINAGE & CULVERTS  DOE STREET 2021-1 

                 

  1. Culverts in front of Diedrich’s Clean out a total of 120 feet. Shoot to Grade from Tee street Culvert 120 feet East to Diedrich’s Second Drive way.

        2. Install 12” Culverts 20’ length with Aprons on driveways. on Stahl’s, Thompson’s & Kruse’s driveways.

        3. Any unforeseen overages must be council approved.

 

                          Proposed bids are due back by March 5, 2021 Opened on March 9,2021 at 7:00 pm.

                        Any delays after May 30,2021 will be subject to a penalty of 250.00 per day.

                                         City of Bruce has the Right to refuse any or all bids.

                 Any questions call City Maintenance at 651-3873 or City office 627-5323

 

 

                      Culvert cost 3- 20’ culverts with aprons cost $1,131.00        

********************************************************************************************************************************************************************************************************************

                                                                                                                                                         

                                                              CITY OF BRUCE                                     

                       PROJECT NAME: DEMOLITION  OF 533 THIRD STREET.

                 

 Proposed bids are due back no later than March 5,2021 Opened and Awarded at the March 9, 2021 at the Bruce City Council meeting. Open to the public. City of Bruce has the Right to refuse any or all bids.

                              Start date March 10,2021 Completion date no later than May 10,2021

                       Any delays after May 10,2021 will be subject to a penalty of 250.00 per day.

  1. Building size 30’ X 52’ Basement Cement walls with cement floor Main level Wood Construction with Asphalt shingles.
  2. The City of Bruce hired Prairie Environmental for Asbestos inspection & removal of any Asbestos this report is available upon request.
  3. The City of Bruce will pay for all Building materials hauled to the Brookings Landfill.
  4. All Costs with removal of building, back fill and Compaction must be included in bid.
  5. Water & Sewer lines must be dug up and caped before Demolition begins.
  6. All Electric lines are removed (Any questions call Joey D. 605-881-3028)
  7. All trucking must use 365B west of Bruce In & Out of Town.
  8. Any unforeseen overages must be council approved.

 

 

       Any Questions Call City Maintenance at 651-3873 or City Office 627-5323


******************************************************************************************************************************************************************************************************************

     COMPLETED                                                        CITY OF BRUCE

                                       PROJECT NAME: CAMPGROUND ROAD EXPANSION 2021-1                

                                                   BUILDING SITE ADDRESS 418 MADISON STREET

                                      Project consists of 14’ X 365’ Road & 10 Camping pads 12’ X 80’

This project has a start date of April 15,2021 & A Completion date of May 15, 2021

Any delays will be subject to Penalty of 250.00 per working Day. City of Bruce has the right

to refuse any or all bids.

 

Proposed bids are due back by March 5,2021 and opened March 9,2021 at 7:00 pm.

        1. Remove sod & black dirt 4 to 6 inches haul dirt & sod to North end of ballpark.

                During the process the dirt at ballpark must leveled to grade for seeding at a later date.

        2. All area dug out on the campground road and 10 camping pads must be covered with

                Crushed Gravel about 550 tons must be laid out & compacted for use.

        3. Any unforeseen overages must be council approved.

  

     A copy of the map is sent with bid. Any questions call City Maintenance at 651-3873


*******************************************************************************************************************************************************************************************************************

COMPLETED                                                        CITY OF BRUCE

                                    PROJECT NAME: CAMPGROUND ELECTRICAL EXPANSION  2021-1                

                                                                     BUILDING SITE ADDRESS

                                                                        418 MADISON STREET

                                            Project consists of 6 Electrical Boxes 1 per camping pad.

       Proposed bids are due back by March 5,2021 & Opened on March 9,2021 at 7:00 pm.

                     Start date April 15,2021 & Completed by May 15,2021

     Any delays after May 15,2021 will be subject to a penalty of 250.00 per day.

                                            City of Bruce has the Right to refuse any or all bids.

  1. 6 New (ELECTRICAL BOXES PROVIDED BY THE CITY OF BRUCE) WITH 50 amp. 30 amp. RV plus 20 amp. GFI. All wire and other supplied Provided by contractor.

       2. All wire from the electrical pole to meter boxes provide by Otter Tail (contact Joey Denison cell 605-881-3028)

       Any Questions Call City Maintenance at 651-3873 or City Office 627-5323